The following sewer pipeline, manhole, and lift station rehabilitation are scheduled. Detailed construction and schedule information on each project is provided below:
- Price Road: Loop 202 Santan Fwy to Queen Creek Road
- Price Road: Frye Road to Elliot Road
- Chandler Boulevard and 56th Street: 56th Street from Frye to Pecos
- Chandler Lift Stations Rehabilitation
The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from just south of the Loop 202 Santan Fwy to Queen Creek Road, and then further south slightly to the Ocotillo Water Reclamation Facility (OWRF) at the southwest corner of Price Rd and Queen Creek Rd. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.
Bypass Installation Continues in Price Road: Crews are currently installing a sewer bypass to bypass wastewater flows from the existing sewer pipeline to nearby manholes for work to take place in the existing pipeline. The bypass pipe is being buried below the asphalt surface to better accommodate travel during the sewer pipeline rehabilitation process.
Traffic control remains in place 24/7 to protect the work zone until a large enough segment of asphalt can be applied to be able to restore the road to normal travel. This asphalt application is somewhat temporary in nature to accommodate protecting the bypass pipe beneath the road surface, but also permitting travel on the roadway. Late next year, after pipeline rehabilitation is complete, the asphalt and bypass pipes will be removed, and permanent restoration of asphalt will take place.
Crews have been working in various locations along Price Road to install lateral lines for bypass, and water crossings to accommodate cleaning the pipeline as part of the rehabilitation process.
Scheduled to take place Wednesday and Thursday, Nov. 20 - 21, beginning as early as 8 a.m. each day, crews will pave back the lateral lines along southbound Price Road, from approximately Spectrum Boulevard to Innovation Street, and will also pave back the recent bypass installation in this area. Southbound Price Road traffic will be reduced to one lane to accommodate this work, shifted to the curb lane on Nov. 20, and shifted to the high-speed lane (nearest the median) on Nov. 21.
Scheduled to take place on Friday, Nov. 22, paving crews will pave back the area where the bypass pipe was recently installed across Queen Creek Road, west of Price Road. Queen Creek Road will be reduced to one lane in each direction, west of Price Road, with traffic first shifted to the curb lanes, and later shifted to the center lanes, to accommodate the paving activity. Please obey traffic signage as it is placed for the safety of crews and travelers.
Work will continue to install bypass pipe off the roadway west of Price Road, from Germann Road to Queen Creek Road.
Work also continues to excavate and construct a manhole south of Queen Creek Road on the west side of Price Road, off the roadway. This work is expected to take about 1-2 weeks to complete. Work will soon begin to construct two additional manholes off the roadway south of Queen Creek Road on the west side of Price Road.
As a note, the bypass pipe consists of five 18" pipes to be able to efficiently convey wastewater flows out of the existing 66" sewer pipeline for rehabilitation to take place. The bypass is generally installed just below the road surface, with some exceptions, from the Loop 202 to Germann Road, and also across Queen Creek Road. There may be brief restrictions as this work takes place across side streets or driveways. Once put into operation, the bypass will be monitored 24/7 for the sewer rehabilitation process to begin.
Sewer Rehabilitation (Pipe Lining): Scheduled to begin in December 2024, the sewer rehabilitation process will begin. This effort includes stationing equipment at various manhole locations to clean and then insert a lining in the existing sewer pipeline, which is then cured to create a permanent lining within the pipe. In addition, several manholes along the alignment require full replacement.
Work to install the bypass is primarily conducted during night hours, and the lining and curing process will take place during daytime hours. However, once the lining curing process begins, it may run into evening or night hours based on the length of the lining and curing process. Night work may be required for work in Price Road nearest Loop 202 Santan Freeway. As sewer rehabilitation completes in late 2025, the bypass removal and restoration will begin, with project completion scheduled for February 2026.
During construction, roads will remain open for travel with lane reductions and possible turn restrictions in place. Night work may be required for work in Price Road nearest Loop 202 Santan Freeway. (WW2302.401)
ADOT is currently working on a project near this area to widen the Loop 202 Santan Freeway. For more information, visit Loop 202.
For questions or further information related to this work, please contact us.
Project Hotline: 480-898-4060
The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from south of Frye Road to Elliot Road. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.
Crews have completed installation of the sewer bypass pipe along nearby side streets of Mission Park Road, Coronado Street and Linda Lane and are currently bypassing wastewater flows from the existing sewer pipeline to nearby manholes. The sewer rehabilitation (pipe lining) process is taking place in Price Road. This effort includes stationing equipment at various manhole locations to clean and then insert a lining in the existing sewer pipeline, which is then cured to create a permanent lining within the pipe.
Crews are currently working to clean and rehabilitate manholes in northbound Price Road, from north of Ray Road to south of Elliot Road. To accommodate this work, traffic is shifted away from the work area, maintaining at least one lane on Price Road, north of Ray Road.
Crews have begun the removal of the sewer bypass pipe and restoration of impacted areas. Work to remove the bypass from Ray Road will take place during night hours to minimize the impact to traffic. The bypass should be completely removed by early to mid-October.
Unless noted, roads will remain open for travel during this work with traffic shifted away from the work area, and lane and possible turn restrictions in place, as needed. Work is primarily taking place during daytime hours; however, during the lining curing process, work may run into evening or night hours based on the length of the lining and curing process. Project completion is scheduled for Fall 2024.
For questions or further information related to this work, please contact us.
Project Hotline: 480-898-4060
The City of Chandler has contracted with FPS Civil to rehabilitate sewer manholes in Chandler Blvd, from west of 54th St to Beck Ave, and in 56th St, from Chandler Blvd to Pecos Rd.
Crews are currently working to complete any punchlist items for final completion. Traffic control will be in place, as needed, at locations requiring repair work.
Access to residences and businesses will be maintained. (WW2208.402)
For questions or further information related to this work, please contact us.
Project Hotline: 480-898-4060
The City of Chandler has contracted with MGC Contractors to rehabilitate several wastewater lift stations throughout Chandler to make repairs or upgrades. Work will typically take place on-site at the lift station; however, traffic restrictions may be needed in some instances to accommodate the work activity as many of these sites have limited space available. Work will typically take place during daytime hours, weekdays (excluding major holidays). A map of the planned locations and current tentative schedule is provided.
For questions or further information related to this work, please contact us.
Project Hotline: 480-898-4060