Sewer Manhole & Pipeline Rehab Projects

The following sewer pipeline, manhole, and lift station rehabilitation are scheduled. Detailed construction and schedule information on each project is provided below:

  • Price Road: Loop 202 Santan Fwy to Queen Creek Road
  • Price Road: Frye Road to Elliot Road
  • Chandler Boulevard and 56th Street: 56th Street from Frye to Pecos
  • Chandler Lift Stations Rehabilitation
Price Road Sewer Pipeline Rehabilitation (Loop 202 Santan Fwy to Queen Creek Road)
Price Road: Loop 202 Santan Freeway to Queen Creek Road

The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from just south of the Loop 202 Santan Fwy to Queen Creek Road, and then further south slightly to the Ocotillo Water Reclamation Facility (OWRF) at the southwest corner of Price Rd and Queen Creek Rd. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.

Construction is not scheduled to begin until July 2024 with sewer bypass set-up taking place to prepare for the lining process.

During construction, roads will remain open for travel with lane reductions and possible turn restrictions in place. Night work may be required for work in Price Road nearest Loop 202 Santan Freeway. (WW2302.401)

For questions or further information related to this work, please contact us.

Project Hotline: 480-898-4060 

Price Road Sewer Pipeline Rehabilitation (Frye Road to Elliot Road)

The City of Chandler has contracted with B&F Contracting to rehabilitate the sewer pipeline in Price Road, from south of Frye Road to Elliot Roa. The “trenchless” technology of lining the sewer pipeline extends the life of the sewer pipeline and is less impactful and of shorter duration than removal and replacement.

Price Road Sewer Rehab Project Area

Sewer bypass pipe bypass pipe is currently in place to bypass wastewater flows from the existing sewer pipeline to nearby manholes. The sewer rehabilitation (pipe lining) process is currently taking place along Price Road. This effort includes stationing equipment at various manhole locations to clean and then insert a lining in the existing sewer pipeline, which is then cured to create a permanent lining within the pipe.

Crews are currently working in manholes in the Chandler Boulevard median, east of Price Road. To accommodate this work, traffic is shifted away from the median in this area.
 
Crews are also currently working the next couple of weeks to rehabilitate sewer pipeline in northbound Price Road, south of Chandler Boulevard. Price Road remains open for travel with lane reductions in place to shift traffic away from the work area.
 
Scheduled to begin June 3, the bypass will be extended to the south to accommodate sewer pipeline rehabilitation from Frye Road to the south. To accommodate this work, Fairview Street will be CLOSED on the east side of northbound Price Road for approximately 3-4 weeks. Access from northbound Price Road to Fairview Street will be provided at Frye Road to Bracken Lane. Detour signage will be in place to direct travelers around the closure. Once the bypass is extended, crews will begin the rehabilitation (pipe lining) process in Price Road, from Fairview Street to Frye Road.
 
Scheduled to take place through June 21, lane reductions are in place for southbound Price Road traffic at Chandler Boulevard, still allowing left turns, right turns, and one thru southbound lane at Chandler Boulevard. These restrictions are necessary to facilitate work in manholes in the Chandler Boulevard/Price Road intersection on the west side of the Loop 101. 

Unless noted, roads will remain open for travel during this work with traffic shifted away from the work area, and lane and possible turn restrictions in place, as needed. Work will primarily take place during daytime hours; however, the lining curing process may run into evening or night hours based on the length of the lining and time needed for the curing process. Once work is complete in all areas, the sewer bypass will be removed, and restoration will take place. Project completion is scheduled for Fall 2024. (WW2210.401)

For questions or further information related to this work, please contact us. 

Project Hotline: 480-898-4060 

Sewer Manhole Rehabilitation Project
Chandler Blvd-56th St Sewer Rehab Project Area

The City of Chandler has contracted with FPS Civil to rehabilitate sewer manholes in Chandler Blvd, from west of 54th St to Beck Ave, and in 56th St, from Chandler Blvd to Pecos Rd. Roads remain open for travel during work with lane and possible turn restrictions in place during work hours to shift traffic away from the work zone.

Scheduled to take place Saturday, June 22, crews will patch back the sewer manholes recently rehabilitated at Chandler Blvd/56th St and at Chandler Blvd just west of 54th St (near Southgate Dr). This work will take place during daytime hours, and crews will return on Saturday, June 29, to pour concrete collars at these manholes to complete this work

Scheduled to begin Monday night, June 24, crews will work in 56th St, between Fairview St and Pecos Rd, in the northbound lanes during night hours to rehabilitate four manholes in this area. This work is being conducted during night hours, 7 p.m. – 5 a.m., Monday through Thursday nights, to limit the impact to the traveling public and the nearby businesses. Traffic will be shifted away from the work area maintaining at least one lane in each direction.   

During off-work hours traffic control will be removed to restore the road to normal travel, and this night work is expected to take 2-3 weeks to complete.

Following this work from Fairview to Pecos, crews will work to complete any punchlist items before final completion. Traffic control will be in place, as needed, at locations requiring repair work.

Access to residences and businesses will be maintained and thank you for your patience during this work. (WW2208.402)

For questions or further information related to this work, please contact us. 

Project Hotline: 480-898-4060 

Sewer Lift Station Rehabilitation Project

The City of Chandler has contracted with MGC Contractors to rehabilitate several wastewater lift stations throughout Chandler to make repairs or upgrades. Work will typically take place on-site at the lift station; however, traffic restrictions may be needed in some instances to accommodate the work activity as many of these sites have limited space available. Work will typically take place during daytime hours, weekdays (excluding major holidays).  A map of the planned locations and current tentative schedule is provided. 

Chandler Lift Station Location Map
Chandler Lift Station Schedule

For questions or further information related to this work, please contact us.

Project Hotline: 480-898-4060